PIRELLI - ENEL PRODUCTION |
![]() |
|
SAN GIOBBE - SACCA SERENELLA POWER LINE 132 KV - 2001 Electric line 132 KV submarine and land pipe for primary cabins linking of S. giobbe (VE) - Sacca Selenella/Murano (VE) - Mestre/Barche, Comune di Venezia - 2001 CHARACERISTICS OF THE WORK Global laying development: Characteristics of cables: Set up: continuos section to those set up in bunch in one dappling on laying strut Partial development per every section: Execution timing: 40 working days |
|
![]() |
|