PIRELLI - ENEL PRODUCTION



SAN GIOBBE - SACCA FISOLA POWER LINE 132 KV - 1997

Electric line 132 KV submarine and land pipe for primary cabins linking of S. giobbe (VE) - Sacca Fisola in Venezia - 1997

CHARACERISTICS OF THE WORK

Global laying development:
• 2.906 ml at 2,00 m marine ditching
• 670 ml at 3,00 m marine ditching

Characteristics of cables:
• single energy cables Ø 120 mm - weight 33,5 Kg/ml
• bunch energy cables (3x120) Ø 260 mm - weight 104,9 Kg/ml

Set up: continuos to those set up in bunch in one dappling on laying strut

Execution timing: 32 working days
Laying production: 320 ml per day